Alashwal, N and Alashwal, A (2023) Rural access programs in Yemen: delay of international funded road projects. Engineering, Construction and Architectural Management, 30(04), 1746-67.
Alsulami, H, Serbaya, S H, Rizwan, A, Saleem, M, Maleh, Y and Alamgir, Z (2023) Impact of emotional intelligence on the stress and safety of construction workers' in Saudi Arabia. Engineering, Construction and Architectural Management, 30(04), 1365-78.
Amiri, R, Majrouhi Sardroud, J and Momenaei Kermani, V (2023) Decision support system for tower crane location and material supply point in construction sites using an integer linear programming model. Engineering, Construction and Architectural Management, 30(04), 1444-62.
Andersen, M (2002) Light distribution through advanced fenestration systems. Building Research & Information, 30(04), 264–81.
Cheraghi, E, Zohrehvandi, S, Vanhoucke, M and Mohamadpour Tosarkani, B (2023) A multiproject scheduling and resource management model in projects construction. Engineering, Construction and Architectural Management, 30(04), 1578-600.
Du, H, Han, Q, Sun, J and Wang, C C (2023) Adoptions of prefabrication in residential sector in China: agent-based policy option exploration. Engineering, Construction and Architectural Management, 30(04), 1697-725.
Du, J, Xue, Y, Sugumaran, V, Hu, M and Dong, P (2023) Improved biogeography-based optimization algorithm for lean production scheduling of prefabricated components. Engineering, Construction and Architectural Management, 30(04), 1601-35.
Dulaimi, M F, Ling, F Y Y, Ofori, G and Silva, N D (2002) Enhancing integration and innovation in construction. Building Research & Information, 30(04), 237–47.
Ebekozien, A, Aigbavboa, C O, Aigbedion, M, Ogbaini, I F and Aginah, I L (2023) Integrated project delivery in the Nigerian construction sector: an unexplored approach from the stakeholders’ perspective. Engineering, Construction and Architectural Management, 30(04), 1519-35.
Fuller, R J and Luther, M B (2002) Thermal simulation of an Australian university building. Building Research & Information, 30(04), 255–63.
Greenwood, D and Wu, S (2012) Establishing the association between collaborative working and construction project performance based on client and contractor perceptions. Construction Management and Economics, 30(04), 299-308.
Guo, H and Lu, W (2023) Measuring competitiveness with data-driven principal component analysis: a case study of Chinese international construction companies. Engineering, Construction and Architectural Management, 30(04), 1558-77.
Hatamleh, M T, Moynihan, G P, Batson, R G, Alzarrad, A and Ogunrinde, O (2023) Risk assessment and ranking in the developing countries’ construction industry: the case of Jordan. Engineering, Construction and Architectural Management, 30(04), 1344-64.
Hu, H, Deng, X and Mahmoudi, A (2023) A cognitive model for understanding fraudulent behavior in construction industry. Engineering, Construction and Architectural Management, 30(04), 1423-43.
Huang, C-F and Lien, H-C (2012) An empirical analysis of the influences of corporate social responsibility on organizational performance of Taiwan's construction industry: using corporate image as a mediator. Construction Management and Economics, 30(04), 263-75.
Ibrahimkhil, M H and Hadidi, L (2023) Is the construction site a safer place under the USACE or local government guidelines? The case of Afghanistan. Engineering, Construction and Architectural Management, 30(04), 1379-400.
Kohler, N and Hassler, U (2002) The building stock as a research object. Building Research & Information, 30(04), 226–36.
Laar, M and Grimme, F W (2002) German developments in guidance systems: an overview daylight. Building Research & Information, 30(04), 282–301.
Lee, C (2023) Evaluating construction delays using productivity-based resource reallocation for economic feasibility. Engineering, Construction and Architectural Management, 30(04), 1679-96.
- Type: Journal Article
- Keywords: delay liquidated damages; goal programming; incentive; productivity; reducing duration
- ISBN/ISSN:
- URL: https://doi.org/10.1108/ECAM-09-2019-0503
- Abstract:
Purpose: Work crew productivity and the application of limited resources are necessary elements in construction duration delay analysis. This study thus proposes a method to analyze construction delays and resource reallocation based on work crew productivity and resource constraints. The study also presents an economic feasibility analysis that maximizes economic effect by reducing construction duration, the cost of resource reallocation, delay liquidated damages (DLDs) and incentives for reducing contractual duration. Design/methodology/approach: The proposed method involved three steps. First, work crew characteristics such as productivity, unit price and workload helped analyze delay information, including delay duration, reducible duration and daily reduced cost. Next, a goal programming method assessed resource reallocation based on the priority (as determined by decision-makers) of each constraint condition, such as the available number of workers, cost, goal workload and statutory working hours. Lastly, the level of reallocation was analyzed based on the results of the economic feasibility analysis and decision-makers’ delay attitudes. Findings: A case study was performed to test the proposed method’s applicability. Its involved sensitivity analysis indicated proposing to decision-makers a scenario based on the prioritization of economic feasibility. The proposed method’s applicability proved high for decision-makers, as they can determine whether to reduce construction duration per the proposed data. Originality/value: The proposed method’s main contribution is the reallocation of resources to reduce construction duration based on work crew productivity and the prioritization of limited resources. The proposed method can analyze the differences in productivity between the plan and actual progress, as well as calculate the necessary number of workers. Decision-makers can then reduce the appropriate level of contractual duration based on their own delay attitude, constraint condition prioritization and results from daily economic feasibility analyses.
Li, J, Zhou, G, Li, D, Zhang, M and Zhao, X (2023) Recognizing workers' construction activities on a reinforcement processing area through the position relationship of objects detected by faster R-CNN. Engineering, Construction and Architectural Management, 30(04), 1657-78.
Liu, J, Wang, Y and Wang, Z (2023) Multidimensional drivers: exploring contractor rule violations in the construction industry. Engineering, Construction and Architectural Management, 30(04), 1496-518.
Mahdavian, S, Lu, M and Pereira, E (2023) Application framework for safety-centric construction acceleration planning. Engineering, Construction and Architectural Management, 30(04), 1401-22.
MarchwiĆski, J and Kurtz-Orecka, K (2023) Effect of photovoltaic installation power and façade glazing ratio on the energy performance of a nursery building. Engineering, Construction and Architectural Management, 30(04), 1463-80.
Mirzaee, A M, Hosseini, M R, Martek, I, Rahnamayiezekavat, P and Arashpour, M (2023) Mitigation of contractual breaches in international construction joint ventures under conditions of absent legal recourse: case studies from Iran. Engineering, Construction and Architectural Management, 30(04), 1481-95.
Rose, T M and Manley, K (2012) Adoption of innovative products on Australian road infrastructure projects. Construction Management and Economics, 30(04), 277-98.
Scala, N M, Liu, M, Alves, T C L, Schiavone, V and Hawkins, D (2023) The gold standard: developing a maturity model to assess collaborative scheduling. Engineering, Construction and Architectural Management, 30(04), 1636-56.
Shojaei, R S, Oti-Sarpong, K and Burgess, G (2023) Enablers for the adoption and use of BIM in main contractor companies in the UK. Engineering, Construction and Architectural Management, 30(04), 1726-45.
Stehn, L (2002) Environmental labelling of timber-framed dwellings and their building components. Building Research & Information, 30(04), 248–54.
Thomson, D, Kaka, A, Pronk, L and Alalouch, C (2012) The use of freelisting to elicit stakeholder understanding of the benefits sought from healthcare buildings. Construction Management and Economics, 30(04), 309-23.
Tu, B, Zuo, J, Chang, R D, Webber, R J, Xiong, F and Dong, N (2023) A system dynamic model for assessing the level of BIM implementation in construction phase: a China case study. Engineering, Construction and Architectural Management, 30(04), 1321-43.
Xue, J, Shen, G Q, Deng, X, Ogungbile, A J and Chu, X (2023) Evolution modeling of stakeholder performance on relationship management in the dynamic and complex environments of megaprojects. Engineering, Construction and Architectural Management, 30(04), 1536-57.
Zhou, Q, Chen, S, Deng, X and Mahmoudi, A (2023) Knowledge transfer among members within cross-cultural teams of international construction projects. Engineering, Construction and Architectural Management, 30(04), 1787-808.
Zhou, S, Qin, L, Zhang, J and Cao, X (2023) Research on the influencing factors of knowledge transfer among construction workers based on social cognitive theory. Engineering, Construction and Architectural Management, 30(04), 1768-86.